FIREFIGHTING SCOPE OF WORK
- Submission of project documents (Material Submittal, Method of Statement, and ITP).
- Submission of Shop Drawing related to Fire Fighting System based on the IFC Drawings, Project Specifications, QCS 2014, and Material Submittal & QCDD Requirement.
- Submission of RFI (Request for Information) if there is any discrepancy in the drawings & specifications., afterword’s incorporate REI reply with shop drawing & material submittal.
- Submission of Hydraulic Calculation for Fire Pump Set, FM 200 Systems.
- Supply, Installation, Testing & Commissioning of Fire Pump including Pump Room Valve, Fuel Tank, Flow Meter and all the necessary items according to QCDD Requirement.
- Supply, Installation, Testing & Commissioning of Fire Fighting System including GI Pipe, Sprinklers, Fire Hose Reel Cabinet, ZCV, ACV, Fire Hydrant and all the necessary accessories according to shop drawing, project specification & QCDD Requirement.
- Supply, Installation, Testing & Commissioning of FM 200 Systems.
- Submission of all the documents related to QCDD Approval.
- Attending for QCDD inspection to obtain the QCDD approval.